On September 1, 2021 Eversource Gas of Massachusetts submitted their Comprehensive Safety Assessment and Implementation Plan required by the DPU 20-59 docket for the acquisition of the Columbia Gas assets. Within that Plan, they listed the ~$40M Western Mass Reliability Project, the previous Longmeadow Supply Strategy Project of Columbia’s 5-part Reliability Project introduced in 2017, to include the new meter station at the Longmeadow Country Club and the high pressure main leaving that station up to the existing Bliss St. Station in Springfield.
On October 8, 2021 Eversource published their project website to support the project and announced Open Houses for November 9 and 10.